Central Plains / Eagle Materials

Project Name: Limestone Blending Storage Stacker and Reclaimer

Project Location: Tulsa, OK

Project Duration: On time, on budget

Project Value: $2.1 million

  • Installed the new Bedeschi blending stacker and reclaimer system – included installation of more than 4,000 feet of new rail
  • Installed 1100′ long belt and a series of four new additive feeder hoppers
  • Installed 1000′ long reclaimer belt, including a traveling tripper to feed the newly modified material hoppers