Ash Grove High-Efficiency Separator

Project Name: High-Efficiency Separator

Project Location: Louisville, NE

Project Duration: 7 months, including 4-week tie-in period for each of the two mill systems

Project Value: $4.6 million

  • Installed two new high-efficiency separators within existing cement milling systems
  • Demoed existing structural steel, concrete, and existing separators, air slides, fans, and dust collectors
  • Constructed new supporting steel, ID fan concrete foundations, high-efficiency separators, ID fans, dust collectors, air slides, chute work, nuisance vent ductwork, process ductwork, and piping
  • Supplied structural steel, process duct-work, piping, chutes, and electrical installation and component