Central Plains / Eagle Materials
Project Name: Limestone Blending Storage Stacker and Reclaimer
Project Location: Tulsa, OK
Project Duration: On time, on budget
Project Value: $2.1 million
- Installed the new Bedeschi blending stacker and reclaimer system – included installation of more than 4,000 feet of new rail
- Installed 1100′ long belt and a series of four new additive feeder hoppers
- Installed 1000′ long reclaimer belt, including a traveling tripper to feed the newly modified material hoppers