Holcim Trident Project

Project Name: Baghouse & Sorbent System

Project Location: Three Forks, MT

Project Duration: 5 months, plus 3-week tie-in period

Project Value: $2 million

  • New process baghouse for cement kiln operations.
  • Installed baghouse, ID fan, dry sorbent-injection system, and pneumatic conveying as well as all associated ductwork, structural steel, siding, and piping.
  • Supplied structural steel, process ductwork, and piping.